CBSE Class 10 Maths (Standard) 2017 · Paper 30(B) · Question 23

Arithmetic Progressions 4 marks Medium
In a construction work, a contractor has to pay penalty for delay beyond a certain date as follows : for the first day, for the second day, for the third day and so on. How much money does the contractor have to pay as penalty, if he has delayed the work by days ? Why is completing any work on time a must ?

Answer

The contractor must pay as penalty. Completing work on time avoids growing penalties and financial loss and reflects discipline and responsibility.